Exercise: Time & Work
Questions for: Efficiency and Time Calculations
Ama can complete a project in 20 days. Ben is 25% more efficient than Ama. They start working on the project together. After 8 days, Ben leaves, and Ama finishes the remaining work alone.
How many additional days did Ama work to complete the remaining project?
A: They start working on the project together. After 8 days, Ben leaves, and Ama finishes the remaining work alone.
How many additional days did Ama work to complete the remaining project?
A. 2 days
B: 3 days
C: 4 days
D: 5 days
Answer: A
1. Ama's daily work rate = 1/20 of the project.
2. Ben is 25% more efficient than Ama, so Ben's daily work rate = 1.25 * (1/20) = 5/4 * (1/20) = 1/16 of the project.
3. Their combined daily work rate = (1/20) + (1/16) = (4/80) + (5/80) = 9/80 of the project.
4. Work done by Ama and Ben together in 8 days = 8 * (9/80) = 72/80 = 9/10 of the project.
5. Remaining work = 1 - (9/10) = 1/10 of the project.
6. Time taken by Ama to complete the remaining 1/10 work = (1/10) / (1/20) = 2 days.
Why others are wrong:
A — Correct answer based on calculations.
B — Results from miscalculation of the remaining work or Ama's finishing time.
C — Occurs if Ben's efficiency or the combined work rate is miscalculated.
D — Could be a result of an incorrect interpretation of work remaining or Ama's rate.
Anya, Ben, and Chloe are collaborating on a project report. Anya can complete the report alone in 20 hours. Ben is 25% more efficient than Anya. Chloe is 50% less efficient than Ben.
If Anya and Chloe work together for 5 hours, and then Ben joins them, how many additional hours will it take for all three to complete the remaining report?
A: Chloe is 50% less efficient than Ben.
If Anya and Chloe work together for 5 hours, and then Ben joins them, how many additional hours will it take for all three to complete the remaining report?
A. 95/23 hours
B: 100/23 hours
C: 85/23 hours
D: 90/23 hours
Answer: A
1. **Calculate individual efficiencies:**
* Anya's efficiency: 1/20 report per hour.
* Ben's efficiency: Ben is 25% more efficient than Anya, so his efficiency is (1/20) * 1.25 = 1/16 report per hour. (Ben completes the report in 20 / 1.25 = 16 hours).
* Chloe's efficiency: Chloe is 50% less efficient than Ben, so her efficiency is (1/16) * (1 - 0.50) = (1/16) * 0.50 = 1/32 report per hour. (Chloe completes the report in 16 / 0.50 = 32 hours).
2. **Calculate work done by Anya and Chloe in the first 5 hours:**
* Combined efficiency of Anya and Chloe = 1/20 + 1/32 = 8/160 + 5/160 = 13/160 report per hour.
* Work done in 5 hours = (13/160) * 5 = 65/160 = 13/32 of the report.
3. **Determine the remaining work:**
* Remaining work = 1 - 13/32 = 19/32 of the report.
4. **Calculate the combined efficiency of Anya, Ben, and Chloe:**
* Combined efficiency (Anya + Ben + Chloe) = 1/20 + 1/16 + 1/32 = 8/160 + 10/160 + 5/160 = 23/160 report per hour.
5. **Calculate the time needed to complete the remaining work:**
* Time = Remaining Work / Combined Efficiency = (19/32) / (23/160) = (19/32) * (160/23) = 19 * (160/32) / 23 = 19 * 5 / 23 = 95/23 hours.
Why others are wrong:
A — This is the correct calculation.
B — This could result from an error in calculating the initial work done, for instance, if only 12/32 of the report was completed, or miscalculation of combined efficiency.
C — This could result from an error in calculating Chloe's efficiency (e.g., if 50% less efficient was interpreted as 50% of Anya's efficiency, or other miscalculations).
D — This could result from various miscalculations in individual efficiencies or the initial work completed before Ben joined.
Discuss About this Question.
Person A can complete a particular project in 20 days. Person B is 25% more efficient than Person A. Person C requires 30 days to complete the same project individually.
If A, B, and C begin working together, but A leaves after 5 days, how many additional days will B and C take to finish the remaining project?
A: Person C requires 30 days to complete the same project individually.
If A, B, and C begin working together, but A leaves after 5 days, how many additional days will B and C take to finish the remaining project?
A. 65/23 days
B: 2.5 days
C: 13/3 days
D: 115/22 days
Answer: A
1. **Calculate individual daily work rates:**
* A's daily work rate = 1/20 of the project.
* B's efficiency is 25% more than A. So, B's daily work rate = (1/20) * (1 + 0.25) = (1/20) * 1.25 = (1/20) * (5/4) = 5/80 = 1/16 of the project.
* C's daily work rate = 1/30 of the project.
2. **Calculate combined daily work rate of A, B, and C:**
* (1/20) + (1/16) + (1/30)
* Find a common denominator (LCM of 20, 16, 30 is 240):
* (12/240) + (15/240) + (8/240) = (12 + 15 + 8)/240 = 35/240 = 7/48 of the project per day.
3. **Calculate work done in the first 5 days (by A, B, and C):**
* (7/48) * 5 = 35/48 of the project.
4. **Calculate the remaining work:**
* 1 - (35/48) = 13/48 of the project.
5. **Calculate combined daily work rate of B and C (after A leaves):**
* (1/16) + (1/30)
* Find a common denominator (LCM of 16, 30 is 240):
* (15/240) + (8/240) = 23/240 of the project per day.
6. **Calculate additional days for B and C to finish remaining work:**
* Remaining work / (B + C's combined rate) = (13/48) / (23/240)
* (13/48) * (240/23) = 13 * (240/48) / 23 = 13 * 5 / 23 = 65/23 days.
Why others are wrong:
A — This is the correct calculation.
B — This result (2.5 days) would be obtained if B was mistakenly assumed to be 25% *less efficient* (taking 25% *more* time than A, so 20 * 1.25 = 25 days, for a rate of 1/25).
C — This result (13/3 days) would be obtained if only Person B (at a rate of 1/16) was assumed to complete the remaining work of 13/48, ignoring Person C's contribution. (13/48) / (1/16) = (13/48) * 16 = 13/3.
D — This result (115/22 days) would be obtained if B was mistakenly assumed to take 25% *more* time than A (i.e., B takes 25 days to complete the task), leading to incorrect combined work rates.
Discuss About this Question.
Anuj can complete a project in 20 days. Bhavya is 25% more efficient than Anuj. They start working on the project together. After 4 days, Anuj leaves, and Bhavya continues to work alone to complete the remaining part of the project.
How many additional days will Bhavya take to complete the remaining project?
A: 8.8 days
B: 11 days
C: 12.8 days
D: 8 days
Answer: A
Let the total work be 1 unit.
Anuj's daily work rate = 1/20 units/day.
Bhavya is 25% more efficient than Anuj, so Bhavya's efficiency factor = 1 + 0.25 = 1.25.
Bhavya's daily work rate = 1.25 * (1/20) = (5/4) * (1/20) = 1/16 units/day.
Combined daily work rate of Anuj and Bhavya = (1/20) + (1/16) = (4/80) + (5/80) = 9/80 units/day.
Work done by Anuj and Bhavya together in 4 days = 4 * (9/80) = 36/80 = 9/20 units.
Remaining work = 1 - (9/20) = 11/20 units.
Time taken by Bhavya to complete the remaining work = (Remaining work) / (Bhavya's daily work rate)
= (11/20) / (1/16) = (11/20) * 16 = 11 * (16/20) = 11 * (4/5) = 44/5 = 8.8 days.
Why others are wrong:
A — Correct calculation.
B — This would be the time taken if Anuj alone completed the remaining 11/20 of the work (11/20 divided by 1/20 = 11 days).
C — This represents the total time to complete the project (4 days of combined work + 8.8 days of Bhavya's solo work = 12.8 days), not just the additional days Bhavya takes.
D — This result could occur if Bhavya's individual work time was incorrectly estimated as 15 days (e.g., 20 - 25% of 20 = 15 days, instead of 20 / 1.25 = 16 days) leading to an incorrect daily rate of 1/15, and subsequent calculation errors for the remaining work.
Discuss About this Question.
Worker P can complete a specific task in 20 days. Worker Q is 25% more efficient than Worker P.
If Worker P and Worker Q begin working on the task together, but Worker Q leaves after 5 days, how many additional days will Worker P require to complete the remaining portion of the task alone?
A: 8.75 days
B: 9 days
C: 10 days
D: 12.5 days
Answer: A
1. Worker P's daily work rate is 1/20 of the task.
2. Worker Q's efficiency is 25% more than P's. So, Q's daily work rate = (1/20) * 1.25 = (1/20) * (5/4) = 5/80 = 1/16 of the task.
3. Combined daily work rate of P and Q = (1/20) + (1/16) = (4/80) + (5/80) = 9/80 of the task.
4. Work completed by P and Q together in 5 days = (9/80) * 5 = 45/80 = 9/16 of the task.
5. Remaining work = 1 - (9/16) = 7/16 of the task.
6. Time taken by Worker P to complete the remaining 7/16 of the task alone = (Remaining Work) / (P's daily work rate) = (7/16) / (1/20) = (7/16) * 20 = 140/16 = 35/4 = 8.75 days.
Why others are wrong:
A — Correct answer derived from accurate calculation of efficiencies and work completed.
B — Incorrect calculation of remaining work or misapplication of Worker P's rate.
C — Likely assumes both workers have the same efficiency, leading to a miscalculation of combined work and remaining task.
D — Error in calculating the time Worker P needs, possibly using an incorrect remaining work portion or efficiency.
Discuss About this Question.
Ad Slot (Above Pagination)
Discuss About this Question.