Exercise: Time & Work
Questions for: Efficiency and Time Calculations
Two individuals, A and B, collaboratively undertook a project. They could complete the entire project in 12 days if they worked together. A, working alone, would require 18 days to finish the same project.
After A and B have worked together for 4 days, A withdraws from the project. If B needs to complete the remaining work in precisely 15 days, what percentage increase in B's original efficiency is required?
A: 40%
B: 50%
C: 60%
D: 75%
Answer: C
1. **Calculate combined daily work rate**: A and B together complete the project in 12 days, so their combined daily work rate is 1/12 of the project.
2. **Calculate A's daily work rate**: A alone completes the project in 18 days, so A's daily work rate is 1/18 of the project.
3. **Calculate B's original daily work rate**: B's daily work rate = (Combined daily work rate) - (A's daily work rate) = 1/12 - 1/18 = (3 - 2)/36 = 1/36 of the project. This means B alone would take 36 days to complete the project.
4. **Calculate work done in 4 days**: A and B work together for 4 days. Work done = 4 * (1/12) = 4/12 = 1/3 of the project.
5. **Calculate remaining work**: Remaining work = Total work - Work done = 1 - 1/3 = 2/3 of the project.
6. **Calculate B's required daily work rate**: B needs to complete the remaining 2/3 of the project in 15 days. So, B's required daily work rate = (2/3) / 15 = 2/45 of the project.
7. **Calculate percentage increase in efficiency**:
Original efficiency (B's daily work rate) = 1/36.
Required efficiency (B's daily work rate) = 2/45.
To find the percentage increase, use the formula: ((Required Efficiency / Original Efficiency) - 1) * 100%
= ((2/45) / (1/36) - 1) * 100%
= ((2/45) * 36 - 1) * 100%
= (72/45 - 1) * 100%
= (8/5 - 1) * 100%
= (1.6 - 1) * 100%
= 0.6 * 100% = 60%.
Why others are wrong:
A — This percentage would result from an error in calculating the remaining work or the required daily rate.
B — Likely results from a miscalculation of B's original efficiency or an incorrect application of the percentage increase formula.
D — Suggests a significant error in determining B's required work rate or comparing it to the original efficiency.
A project requires 120 man-hours of work to be completed. Initially, a team of 5 workers starts the project, with each worker operating at 60% of the standard efficiency. After 8 hours of work, two workers are unexpectedly reassigned to another critical task.
Assuming the remaining workers continue at the same individual efficiency, how many additional hours will it take to complete the project?
A: 48 hours
B: 50 hours
C: 53 hours and 20 minutes
D: Initially, a team of 5 workers starts the project, with each worker operating at 60% of the standard efficiency. After 8 hours of work, two workers are unexpectedly reassigned to another critical task.
Assuming the remaining workers continue at the same individual efficiency, how many additional hours will it take to complete the project?
A. 48 hours
B. 50 hours
C. 53 hours and 20 minutes
D. 56 hours
Answer: C
1. The total work required is 120 standard man-hours.
2. Each worker operates at 60% of standard efficiency.
3. Initial team efficiency (5 workers) = 5 workers * 0.6 (efficiency per worker) = 3 units of standard work per hour.
4. Work completed in the first 8 hours = 3 units/hour * 8 hours = 24 standard man-hours.
5. Remaining work = 120 standard man-hours - 24 standard man-hours = 96 standard man-hours.
6. After reassignment, the new team size is 5 - 2 = 3 workers.
7. New team efficiency (3 workers) = 3 workers * 0.6 (efficiency per worker) = 1.8 units of standard work per hour.
8. Additional time needed to complete the remaining work = Remaining work / New team efficiency.
9. Additional time = 96 man-hours / 1.8 man-hours/hour = 960 / 18 hours = 160 / 3 hours.
10. 160 / 3 hours = 53 and 1/3 hours, which is 53 hours and 20 minutes.
Why others are wrong:
A — This option might result from an incorrect calculation of remaining work or misapplication of efficiency.
B — This option is likely a result of an arithmetic error in calculating the remaining time.
D — This option indicates an overestimation of the remaining time needed, possibly due to an incorrect remaining work or team efficiency calculation.
Discuss About this Question.
An experienced technician can assemble 6 gadgets per hour. A trainee technician works at 60% of the experienced technician's efficiency.
If both technicians work together on a project requiring the assembly of 192 gadgets, and they work for 8 hours a day, how many days will it take them to complete the project?
A: 2.5 days
B: 3 days
C: 4 days
D: 5 days
Answer: A
1. Calculate the experienced technician's assembly rate: 6 gadgets/hour.
2. Calculate the trainee technician's efficiency: 60% of 6 gadgets/hour = 0.60 * 6 = 3.6 gadgets/hour.
3. Calculate their combined assembly rate per hour: 6 gadgets/hour (experienced) + 3.6 gadgets/hour (trainee) = 9.6 gadgets/hour.
4. Calculate their combined work output per day (working 8 hours): 9.6 gadgets/hour * 8 hours/day = 76.8 gadgets/day.
5. Calculate the total number of days needed to assemble 192 gadgets: 192 gadgets / 76.8 gadgets/day = 2.5 days.
Why others are wrong:
A — This is the correct calculation.
B — This could result from various miscalculations, such as slightly underestimating combined daily output. For example, if the combined daily output was mistakenly calculated as 64 gadgets/day (192/64 = 3).
C — This would be the time taken if only the experienced technician worked (192 gadgets / (6 gadgets/hour * 8 hours/day) = 192 / 48 = 4 days).
D — This could result from incorrectly averaging their individual hourly rates ((6 + 3.6)/2 = 4.8 gadgets/hour) and then calculating based on that (192 / (4.8 * 8) = 192 / 38.4 = 5 days).
Discuss About this Question.
Alex can complete a specific data analysis project in 20 days. Ben, working independently, is 25% more efficient than Alex. They begin working on the project together.
If Alex and Ben work collaboratively for 4 days, and then Alex ceases his involvement, how many additional days will Ben require to finish the remaining portion of the project alone?
A: 7.5 days
B: 8 days
C: 8.8 days
D: 9.2 days
Answer: C
1. Alex's daily work rate is 1/20 of the project.
2. Ben is 25% more efficient than Alex, so Ben's daily work rate is (1/20) * 1.25 = (1/20) * (5/4) = 5/80 = 1/16 of the project.
3. Their combined daily work rate is (1/20) + (1/16) = (4/80) + (5/80) = 9/80 of the project.
4. In 4 days, the work completed by both of them is (9/80) * 4 = 36/80 = 9/20 of the project.
5. The remaining work is 1 - (9/20) = 11/20 of the project.
6. Ben alone will complete the remaining work at his rate of 1/16 per day.
7. Time taken by Ben = (Remaining work) / (Ben's daily work rate) = (11/20) / (1/16) = (11/20) * 16 = 11 * (4/5) = 44/5 = 8.8 days.
Why others are wrong:
A — Incorrect calculation of Ben's efficiency or remaining work, possibly leading to 15/2 of 1/4 (e.g., if Ben's efficiency was miscalculated or remaining work was wrong).
B — May result from rounding or an error in calculating the remaining work or Ben's rate. For instance, if the remaining work was mistakenly calculated as 1/2, or if Ben's rate was incorrectly taken as 1/11.
C — This is the correct calculation.
D — Likely an arithmetic error in the final step or a miscalculation of combined work rate.
Discuss About this Question.
Two artisans, X and Y, are tasked with completing a series of intricate carvings. Artisan X can complete one carving in 18 hours. Artisan Y is 20% less efficient than Artisan X.
If they work together on a single carving, how many hours will it take them to complete it?
A: 8 hours
B: 9 hours
C: 10 hours
D: 12 hours
Answer: C
1. Determine Artisan X's hourly work rate: X completes 1 carving in 18 hours, so X's rate is 1/18 of a carving per hour.
2. Determine Artisan Y's time to complete one carving: Y is 20% less efficient than X, meaning Y's efficiency is 80% (or 0.8) of X's. Therefore, Y will take 1 / 0.80 = 1.25 times longer than X.
3. Calculate Y's time to complete one carving: Y's time = 18 hours * 1.25 = 22.5 hours.
4. Determine Artisan Y's hourly work rate: Y completes 1 carving in 22.5 hours, so Y's rate is 1/22.5, which simplifies to 2/45 of a carving per hour.
5. Calculate their combined hourly work rate: Combined rate = X's rate + Y's rate = 1/18 + 2/45.
6. Find a common denominator for 18 and 45, which is 90: 1/18 becomes 5/90; 2/45 becomes 4/90.
7. Combined rate = 5/90 + 4/90 = 9/90 = 1/10 of a carving per hour.
8. Calculate the total time to complete one carving together: Time = 1 / (Combined rate) = 1 / (1/10) = 10 hours.
Why others are wrong:
A — Incorrect calculation, possibly if Y's efficiency was higher or an error in combining rates.
B — Incorrect calculation, likely an error in interpreting "20% less efficient" or in finding the common work rate.
C — Correct answer.
D — Incorrect calculation, possibly by averaging their individual times or other common mathematical errors in inverse proportionality.
Discuss About this Question.
Ad Slot (Above Pagination)
Discuss About this Question.