Exercise: Time & Work
Questions for: Efficiency and Time Calculations
Worker P can complete a specific task in 20 days. Worker Q is 25% more efficient than Worker P. They begin working together on the task.
After they have worked together for 5 days, Worker Q leaves. How many additional days will Worker P take to complete the remaining portion of the task alone?
A: 7.5 days
B: 8 days
C: 8.5 days
D: 8.75 days
Answer: D
1. **Calculate Worker P's daily work rate:** If P completes the task in 20 days, P completes 1/20 of the task per day.
2. **Calculate Worker Q's daily work rate:** Q is 25% more efficient than P. So, Q's efficiency = P's efficiency × 1.25 = (1/20) × 1.25 = 1.25/20 = 5/80 = 1/16 of the task per day.
3. **Calculate their combined daily work rate:** P + Q = (1/20) + (1/16). The least common multiple (LCM) of 20 and 16 is 80. So, (4/80) + (5/80) = 9/80 of the task per day.
4. **Calculate work done in 5 days:** They worked together for 5 days, so work done = (9/80) × 5 = 45/80 = 9/16 of the task.
5. **Calculate remaining work:** Total work is 1. Remaining work = 1 - (9/16) = 7/16 of the task.
6. **Calculate time Worker P takes to complete remaining work:** Worker P completes 1/20 of the task per day. Time = (Remaining Work) / (P's daily work rate) = (7/16) / (1/20) = (7/16) × 20 = 140/16 = 35/4 = 8.75 days.
Why others are wrong:
A — Incorrect calculation of remaining work or Worker P's time.
B — Arithmetic error in calculating combined efficiency or final division.
C — Miscalculation of individual efficiencies or total work completed together.
D — (This is the correct answer)
Alice, Bob, and Carol are tasked with completing a project. Alice can finish the entire project in 10 days, Bob in 15 days, and Carol in 30 days if each worked alone. They begin working together, but Carol departs after 3 days.
Assuming a constant work rate for each individual, how many additional days will Alice and Bob take to complete the remaining portion of the project?
A: 2.4 days
B: 3 days
C: 4 days
D: 2 days
Answer: A
1. Assume the total work is the Least Common Multiple (LCM) of 10, 15, and 30, which is 30 units.
2. Alice's daily work rate (efficiency) = 30 units / 10 days = 3 units/day.
3. Bob's daily work rate = 30 units / 15 days = 2 units/day.
4. Carol's daily work rate = 30 units / 30 days = 1 unit/day.
5. Combined daily work rate of Alice, Bob, and Carol = 3 + 2 + 1 = 6 units/day.
6. Work done in the first 3 days (by A+B+C) = 6 units/day * 3 days = 18 units.
7. Remaining work = Total work - Work done = 30 - 18 = 12 units.
8. Combined daily work rate of Alice and Bob (after Carol leaves) = 3 + 2 = 5 units/day.
9. Additional days required for Alice and Bob to complete the remaining work = Remaining work / (A+B)'s combined daily rate = 12 units / 5 units/day = 2.4 days.
Why others are wrong:
A — This is the correct calculation.
B — Incorrect if the remaining work was miscalculated or an arithmetic error was made in the final division.
C — Incorrect; likely represents a misunderstanding of how to calculate remaining work or the combined efficiency.
D — Incorrect; suggests a significant error in either the calculation of the remaining work or the combined daily rate of Alice and Bob.
Discuss About this Question.
Machine A can complete a production order in 10 hours. Machine B can complete the same production order in 15 hours. Both machines begin working together on a combined order. After 3 hours, Machine B ceases operation due to a technical fault.
Approximately how much more time, in hours, will Machine A need to finish the remainder of the combined order alone?
A: 5 hours
B: 6 hours
C: 7.5 hours
D: 8 hours
Answer: A
1. Calculate the rate of Machine A: 1/10 of the order per hour.
2. Calculate the rate of Machine B: 1/15 of the order per hour.
3. Calculate their combined rate: (1/10) + (1/15) = 3/30 + 2/30 = 5/30 = 1/6 of the order per hour.
4. Calculate the amount of work completed in the 3 hours they worked together: (1/6) * 3 hours = 1/2 of the order.
5. Determine the remaining work: 1 (total order) - 1/2 (completed) = 1/2 of the order.
6. Calculate the time Machine A needs to complete the remaining work alone: (1/2) / (1/10) = 1/2 * 10 = 5 hours.
Why others are wrong:
A — This is the correct calculation.
B — Incorrectly assumes the remaining work corresponds to half of the total time both machines would take (which is 6 hours for the full order).
C — Incorrectly applies Machine B's rate (15 hours for full order) to the remaining half of the work (15 * 0.5 = 7.5 hours).
D — Results from miscalculation or an incorrect approach, such as subtracting 3 hours from A's total time and then adding extra time without basis.
Discuss About this Question.
Liam can complete a project in 10 days, while Sarah can complete the same project in 15 days. They begin working together, but after 4 days, Sarah leaves. Liam then finishes the remaining work alone.
How many additional days will Liam need to complete the project?
A: 3 1/3 days
B: 5 days
C: 6 days
D: 7 days
Answer: A
Let the total work be the Least Common Multiple (LCM) of 10 and 15, which is 30 units.
Liam's daily work rate = 30 units / 10 days = 3 units/day.
Sarah's daily work rate = 30 units / 15 days = 2 units/day.
Combined daily work rate of Liam and Sarah = 3 units/day + 2 units/day = 5 units/day.
Work done by Liam and Sarah together in 4 days = 5 units/day * 4 days = 20 units.
Remaining work = Total work - Work done = 30 units - 20 units = 10 units.
Time Liam needs to complete the remaining work alone = Remaining work / Liam's daily work rate = 10 units / 3 units/day = 10/3 days = 3 1/3 days.
Why others are wrong:
B — This would be the time if the remaining work was divided by Sarah's rate (10/2 = 5 days), which is incorrect as Liam finishes the work.
C — This represents the total time Liam and Sarah would take to complete the *entire* project if they worked together (30 units / 5 units/day = 6 days), not the additional time Liam takes.
D — This would result from various calculation errors, such as miscalculating the remaining work or Liam's rate.
Discuss About this Question.
Anusha can complete a complex data analysis project in 30 days. Bhanu is 25% more efficient than Anusha. They begin working together on the project.
If Anusha and Bhanu work together for 6 days, and then Anusha leaves, how many more days will Bhanu take to complete the remaining part of the project?
A: They begin working together on the project.
If Anusha and Bhanu work together for 6 days, and then Anusha leaves, how many more days will Bhanu take to complete the remaining part of the project?
A. 13.2 days
B: 12.5 days
C: 14 days
D: 15 days
Answer: A
1. Anusha's daily work rate = 1/30 of the project.
2. Bhanu is 25% more efficient than Anusha. Bhanu's efficiency = 1.25 * Anusha's efficiency.
3. Bhanu's daily work rate = 1.25 * (1/30) = (5/4) * (1/30) = 5/120 = 1/24 of the project.
4. Combined daily work rate of Anusha and Bhanu = (1/30) + (1/24) = (4/120) + (5/120) = 9/120 = 3/40 of the project.
5. Work done by Anusha and Bhanu together in 6 days = 6 * (3/40) = 18/40 = 9/20 of the project.
6. Remaining work = Total work - Work done = 1 - (9/20) = 11/20 of the project.
7. Time taken by Bhanu to complete the remaining work = (Remaining Work) / (Bhanu's daily work rate).
8. Time = (11/20) / (1/24) = (11/20) * 24 = 11 * (24/20) = 11 * (6/5) = 66/5 = 13.2 days.
Why others are wrong:
A — This option is the result of correct calculations.
B — This value typically results from miscalculating Bhanu's efficiency or the remaining work fraction.
C — This value could arise from errors in determining the combined work rate or the total work completed initially.
D — This value often results from a misapplication of the time calculation formula or a miscalculation of the remaining work proportion.
Discuss About this Question.
Ad Slot (Above Pagination)
Discuss About this Question.