Exercise: Time & Work
Questions for: Efficiency and Time Calculations
A large-scale construction project can be completed by Contractor P in 20 days. Contractor Q, working alone, can complete the same project in 30 days. They begin working together, but after 5 days, Contractor P must leave the project due to another urgent commitment. Contractor Q then continues to work alone until the entire project is finished.
How many total days did it take to complete the entire project?
A: 18 days
B: 20 days
C: 22.5 days
D: How many total days did it take to complete the entire project?
A. 18 days
B. 20 days
C. 22.5 days
D. 25 days
Answer: C
1. Calculate the daily work rate for Contractor P: 1/20 of the project per day.
2. Calculate the daily work rate for Contractor Q: 1/30 of the project per day.
3. Calculate their combined daily work rate: 1/20 + 1/30 = 3/60 + 2/60 = 5/60 = 1/12 of the project per day.
4. Calculate the work completed in the first 5 days by both contractors: 5 days * (1/12 project/day) = 5/12 of the project.
5. Calculate the remaining work: 1 - 5/12 = 7/12 of the project.
6. Calculate the time Contractor Q takes to complete the remaining work alone: (7/12 project) / (1/30 project/day) = (7/12) * 30 = 7 * (30/12) = 7 * (5/2) = 35/2 = 17.5 days.
7. Calculate the total days to complete the project: 5 days (initial period) + 17.5 days (Contractor Q alone) = 22.5 days.
Why others are wrong:
A — This might result from an incorrect calculation of the remaining work or Bob's time to complete it, possibly rounding errors or computational mistakes.
B — This could occur if one incorrectly assumed that Q completed the remaining half of the project in 15 days (half of 30) and added it to 5 days, or if P's individual time was mistakenly chosen.
D — This option might be chosen if one incorrectly calculated Q's time for the remaining work (e.g., 7/12 of 30 was miscalculated) or made an error in the initial combined work calculation.
A team of 5 engineers was assigned to complete a project, estimated to take 20 days. After 8 days of work, 2 engineers were reassigned to another critical task and left the team.
How many *additional* days will it take the remaining engineers to complete the project?
A: 20 days
B: 12 days
C: 28 days
D: 30 days
Answer: A
1. Calculate the total work in "engineer-days": 5 engineers * 20 days = 100 engineer-days.
2. Calculate the work done in the first 8 days: 5 engineers * 8 days = 40 engineer-days.
3. Calculate the remaining work: 100 engineer-days (total) - 40 engineer-days (done) = 60 engineer-days.
4. Determine the number of remaining engineers: 5 engineers - 2 engineers = 3 engineers.
5. Calculate the additional days required by the remaining engineers: 60 engineer-days / 3 engineers = 20 days.
Why others are wrong:
A — Correct answer.
B — This would be the remaining days if the original 5 engineers continued without interruption (20 - 8 = 12 days), not accounting for the reduced team size.
C — This is the total time from the start of the project (8 initial days + 20 additional days), not just the additional days required.
D — This results from incorrectly dividing the remaining work by the number of engineers who *left* (60 engineer-days / 2 engineers = 30 days) instead of the engineers who remained.
Discuss About this Question.
Worker A can complete a specific task of producing 500 units in 10 hours. Worker B, who is 25% more efficient than Worker A, begins working on the same task alongside Worker A. After 4 hours, Worker A has to leave due to an emergency, and Worker B continues alone.
How many additional hours will Worker B need to complete a total production target of 1200 units?
A: After 4 hours, Worker A has to leave due to an emergency, and Worker B continues alone.
How many additional hours will Worker B need to complete a total production target of 1200 units?
A. 12 hours
B: 10 hours
C: 15 hours
D: 16 hours
Answer: A
1. Calculate Worker A's efficiency: Worker A produces 500 units in 10 hours, so Worker A's rate is 500 units / 10 hours = 50 units/hour.
2. Calculate Worker B's efficiency: Worker B is 25% more efficient than Worker A. So, Worker B's rate is 50 units/hour * 1.25 = 62.5 units/hour.
3. Calculate work done by Worker A in the first 4 hours: 50 units/hour * 4 hours = 200 units.
4. Calculate work done by Worker B in the first 4 hours: 62.5 units/hour * 4 hours = 250 units.
5. Calculate total work done by both workers in the first 4 hours: 200 units (by A) + 250 units (by B) = 450 units.
6. Calculate remaining work: The total target is 1200 units. Remaining work = 1200 units - 450 units = 750 units.
7. Calculate time for Worker B to complete the remaining work alone: Remaining work / Worker B's rate = 750 units / 62.5 units/hour = 12 hours.
Why others are wrong:
B — This would be the answer if Worker B's efficiency was incorrectly calculated as 50 + 25 = 75 units/hour.
C — This would be the answer if Worker B's efficiency was mistakenly taken as Worker A's efficiency (50 units/hour) for the remaining work.
D — This represents the total time Worker B worked (4 hours initially + 12 hours alone), not the additional hours required.
Discuss About this Question.
Project Alpha needs to be completed. Anil can complete Project Alpha in 20 days working alone. Bala can complete the same project in 30 days working alone. They begin working together, but after 6 days, Anil leaves the project due to an urgent commitment.
Assuming Bala continues working at his usual pace, how many additional days will Bala need to complete the remaining portion of Project Alpha?
A: 12 days
B: 15 days
C: 18 days
D: Anil can complete Project Alpha in 20 days working alone. Bala can complete the same project in 30 days working alone. They begin working together, but after 6 days, Anil leaves the project due to an urgent commitment.
Assuming Bala continues working at his usual pace, how many additional days will Bala need to complete the remaining portion of Project Alpha?
A. 12 days
B. 15 days
C. 18 days
D. 20 days
Answer: B
1. Calculate Anil's daily work rate: 1/20 of the project.
2. Calculate Bala's daily work rate: 1/30 of the project.
3. Calculate their combined daily work rate: 1/20 + 1/30 = (3/60) + (2/60) = 5/60 = 1/12 of the project per day.
4. Calculate the work done in the first 6 days by Anil and Bala working together: 6 days * (1/12 project/day) = 6/12 = 1/2 of the project.
5. Calculate the remaining work: Total work (1) - Work done (1/2) = 1/2 of the project.
6. Calculate the time Bala needs to complete the remaining work alone: Remaining work / Bala's daily work rate = (1/2) / (1/30) = (1/2) * 30 = 15 days.
Why others are wrong:
A — This might be the result of miscalculating the remaining work or applying the wrong rate.
C — Could result from an arithmetic error or an incorrect assumption about the fraction of work remaining (e.g., if one incorrectly thought 3/5 of the work remained).
D — This is Anil's individual time to complete the entire project, not the time for Bala to finish the remaining work.
Discuss About this Question.
An engineering project requires a team to complete it. Person X is twice as efficient as Person Y. If Person Y alone can complete the entire project in 30 days, both X and Y begin working together.
After 4 days, Person X is reassigned to another critical task. How many additional days will Person Y require to complete the remaining portion of the project?
A: 15 days
B: 18 days
C: 20 days
D: 24 days
Answer: B
1. Let the total work be 1 unit.
2. Person Y completes the work in 30 days, so Y's 1-day work rate = 1/30 of the project.
3. Person X is twice as efficient as Y. So, X's 1-day work rate = 2 * (1/30) = 1/15 of the project. (This means X can complete the project alone in 15 days).
4. Combined 1-day work rate of X and Y = (1/15) + (1/30) = (2/30) + (1/30) = 3/30 = 1/10 of the project.
5. Work done by X and Y together in 4 days = 4 * (1/10) = 4/10 = 2/5 of the project.
6. Remaining work = Total work - Work done = 1 - 2/5 = 3/5 of the project.
7. After X leaves, only Y works. Time taken by Y to complete the remaining work = (Remaining work) / (Y's 1-day work rate).
8. Time = (3/5) / (1/30) = (3/5) * 30 = 3 * 6 = 18 days.
Why others are wrong:
A — This could result from an error in calculating the remaining work (e.g., if remaining work was incorrectly taken as 1/2, then 1/2 * 30 = 15).
C — This could arise if the work done together was incorrectly calculated (e.g., if 1/3 of the work was done, remaining 2/3 * 30 = 20).
D — This could result from significant errors in efficiency calculations or remaining work calculation (e.g., if 4/5 of the work remained, then 4/5 * 30 = 24).
Discuss About this Question.
Ad Slot (Above Pagination)
Discuss About this Question.