Exercise: Industrial Engineering And Production Management

Questions for: Industrial Engineering And Production Management

In order to avoid excessive multiplication of facilities, the layout preferred is
A:
product layout
B:
process layout
C:
group layout
D:
static layout
Answer: B
No answer description is available. Let's discuss.
PERT analysis is based upon
A:
optimistic time
B:
pessimistic time
C:
most likely time
D:
all of these
Answer: D
No answer description is available. Let's discuss.
A-B-C analysis is used in
A:
CPM
B:
PERT
C:
inventory control
D:
all of these
Answer: C
No answer description is available. Let's discuss.
Work study involues
A:
only method study
B:
only work measurement
C:
method study and work measurement
D:
only motion study
Answer: C
No answer description is available. Let's discuss.
Which of the following are the guidelines for the construction of a network diagram?
A:
Each activity is represented by one and only one arrow in the network.
B:
Dangling must be avoided in a network diagram.
C:
Dummy activity consumes no time or resource.
D:
all of the above
Answer: D
No answer description is available. Let's discuss.