Exercise: Industrial Engineering And Production Management

Questions for: Industrial Engineering And Production Management

When slack of an activity is positive
A:
it represents a situation where extra resources are available and the completion of project is not delayed
B:
it represents that a programme falls behind schedule and additional resources are required to complete the project in time
C:
the activity is critical and any delay in its performance will delay the completion of whole project
D:
any one of the above
Answer: A
No answer description is available. Let's discuss.
In a thermal power plant, coal from the coal handling plant is moved to the boiler bunker through a
A:
belt conveyor
B:
bucket conveyor
C:
fork lift truck
D:
overhead crane
Answer: A
No answer description is available. Let's discuss.
Break even point is the point where
A:
fixed and variable cost lines intersect
B:
fixed and total cost lines intersect
C:
variable and total cost lines intersect
D:
sales revenue and total expensive lines intersect
Answer: D
No answer description is available. Let's discuss.
Queuing theory is used for
A:
job-shop scheduling
B:
inventory problems
C:
traffic congestion studies
D:
all of these
Answer: D
No answer description is available. Let's discuss.
Acceptance sampling is used in
A:
job production
B:
batch production
C:
mass production
D:
all of these
Answer: C
No answer description is available. Let's discuss.