Exercise: Architectural Working Drawings

Questions for: Architectural Working Drawings

The foundation contractor will work with the following architectural plans.
A:
foundation
B:
site plan
C:
floor plan
D:
all of the above
Answer: D
No answer description is available. Let's discuss.
Once the architect has finalized the house plans with the client any changes to the design requested by the client will require a ________.
A:
change order
B:
modification slip
C:
whole new set of drawings
D:
none of the above
Answer: A
No answer description is available. Let's discuss.
The architectural drafter usually begins a set of working drawings by creating the ________ plan first.
A:
foundation
B:
floor plan
C:
elevations
D:
building section
Answer: B
No answer description is available. Let's discuss.
The text height for room names should be set to ________for a drawing that will be plotted to a scale of ΒΌ" = 1'-0".
A:
4"
B:
5"
C:
6"
D:
8"
Answer: C
No answer description is available. Let's discuss.
The building construction industry relies on sets of ________ drawings to construct homes and commercial buildings.
A:
mechanical
B:
isometric
C:
architectural working
D:
all of the above
Answer: C
No answer description is available. Let's discuss.